2022 RTP Update Progress
Percent complete: 50%

To-date, Fresno COG has identified the following RTP/SCS milestone goal dates. Items in bold lettering below have not yet been completed:

  • Updated Public Participation Plan Adopted – June 25, 2020
  • RTP Roundtable Kick-Off Meeting June 24, 2020
  • Community survey conducted and completed – May through July 2020, results presented and accepted August 26, 2020
  • Programming Technical Working Group, first meeting – July 21, 2020
  • Transportation Needs Survey outreach – September 9- October 15, 2020
  • Environmental Impact Report Request For Proposals released – November 2020
  • Revenue projections, call for projects – fall to early winter 2020
  • Demographic forecast – completed October 2020
  • Environmental Justice Subcommittee – Meets Fall 2020 – Fall 2021 – committee working
  • SCS scenario strategies development – Approved January 2021
  • Draft Policy Element Outline – Approved February 2021
  • Action Element – Beginning development February 2021 – under development
  • SCS scenario strategies public outreach – March/April 2021 – under development
  • Scenario modeling – May to mid-Aug 2021
  • SCS scenario outreach workshops – Early/mid Sept 2021
  • SCS preferred scenario selection (Fresno COG Board) – Oct 2021
  • Conformity – winter 2021 to spring 2022
  • RTP document development – fall 2021 to spring 2022
  • Draft RTP/SCS and associated documents released for 55-day public review and comment – Spring 2022
  • RTP/SCS final adoption by the Fresno COG Policy Board – June 2022
  • Final Environmental Impact Report Adopted – June 2022